3.3 Temporary works procedures
The temporary works process
3.3.8
A simplified temporary works procedure can be established under the following headings.
Stage specified in BS
5975-1:2024 clause 1
1. Conceived
Stage specified in this
Management Guide
1. Identify
2. Plan
2. Designed
3. Specified
3. Design
4. Check design
4. Constructed
5. Build
5. Used
6. Use
6. Dismantled
7. Dismantle
3.3.9
Phase specified in this
Management Guide
Phase specified in CDM
2015
1. Plan
1. Pre-construction
2. Design
3. Build
2. Construction
4. Remove
3. Post-construction
The following table shows a typical temporary works process identifying actions in seven (7)
stages including who could be responsible for a relevant action and the documentation output
required for verification by the TWC. This is for illustration purposes only.