How to manage temporary works in construction management guide preview - Book - Page 76
3.3 Temporary works procedures
3.3.13
The following table shows all relevant roles within the wider project team and who is likely to
appoint them.
Role
Regulation or clause
PD
The Client
Construction (Design and
Management) Regulations
2015 regulation 5
PC
The Client
Construction (Design and
Management) Regulations
2015 regulation 5
PWD
The Client, or PC’s technical team
Construction (Design and
Management) Regulations
2015 regulation 8
The Client or PC
Construction (Design and
Management) Regulations
2015 regulation 8
Their Executive Board
BS 5975-1:2024 clause
5.1.2.1
The PC’s DI
BS 5975-1:2024 clause
8.3.2.1
TWC
The DI of the organisation that employees
them
BS 5975-1:2024 clause
8.3.3.1
TWS
The DI of the organisation that employees
them, or project manager or TWC if
delegated to them by the DI
BS 5975-1:2024 clauses
4.1.2(o) & 8.3.4.1
The PC or managing contractor
Construction (Design and
Management) Regulations
2015 regulation 8
TWD
individual
The DI of the organisation that employees
them, and verified by the PC
BS 5975-1:2024 clause
7.1.1 and 8.4.3
TWDC
company
The PC or managing contractor
Construction (Design and
Management) Regulations
2015 regulation 8
TWDC
individual
The DI of the organisation that employees
them, and verified by the PC
BS 5975-1:2024 clause
7.1.1 and 8.4.3
Supplier
The Client’s, or PC’s commercial or
procurement team
Construction (Design and
Management) Regulations
2015 regulation 8
Their Executive Board
BS 5975-1:2024 clause 9.2
Contractor
DI
PC TWC
TWD company
Supplier DI
76
Who is likely to appoint them?
© mytemporary.works | How to manage temporary works in construction