How to manage temporary works in construction management guide preview - Book - Page 79
3.4 The temporary works implementation plan
Heading
Subheading
5.2
5.3
5.4
3.4.5
Arrangements for co-ordination of on-going design works and
design changes
5.2.1 Permanent works design
5.2.2 Temporary works design
Significant risks identified during design.
5.3.1 Permanent works design
5.3.2 Temporary works design
Materials and equipment requiring precautions
BS 5975-1:2024 clause 13.1.2, states that the PC’s TWC, or Managing Contractors TWC, should
verify that the temporary works implementation plan is in place.
3.4.6
BS 5975-1:2024 clause 13.1.3, states that the temporary works implementation plan
should be developed taking into consideration site conditions, construction programme which
are included into the construction phase plan specifically relating to arrangements for
controlling significant site risk.
3.4.7
BS 5975-1:2024 clause 13.1.2, 13.1.3, 13.1.4 and 13.1.5, describes the contents of the
temporary works implementation plan. These could be included in a specific project file for
each contractor or each structure, or a range of structures that interface with each other.
Temporary works implementation plan
Contents list
1. Temporary works register
2. Appointment letters
3. Design brief
4. Design drawings
5. Design certificate
6. Installation guide and data sheets
7. Risk assessments and method statements
8. Risk assessments and method statements review
9. Inspection and test plan
10. Inspection checklists and reports
11. Permits