4.4 Design checking
4.4.7
Where an interface like this exists, BS 5975-1:2024 clause 8.1.2 states the TWC should manage
the interfaces and where the temporary works scheme involves substantial contributions from
more than one designer, or the TWC requires more technical contribution, BS 5975-1:2024
clause 7.4.2.1 states that a Lead TWD should manage the design interfaces, and their name
should be recorded in the temporary works implementation plan.
4.4.8
BS 5975-1:2024 clause 7.4.2.2 provides the Lead TWD’s responsibilities. BS 5975-1:2024 clause
7.4.2.2(c), states that the Lead TWD should verify design contributions from all designers are
compatible with each other. This is illustrated below.
Principal Contractor
TWC
Lead TWD
Liaise
Principal Designer
External design &
engineering team
TWD
BS
5975-1:2024
clause
7.4.2.2(d), states that the Lead
TWD should obtain a holistic
understanding of the whole
design
External design
checking team TWDC
106
Managing Contractor
TWC
Managing Contractor
TWC
[Groundworks]
[Scaffolding]
[RC Frame]
TWD
TWD
PWD
Liaise
Managing Contractor
TWC