5.1 Execution risk
What the law says about design responsibilities
5.1.1
The Construction (Design and Management) Regulations 2015, regulation 19, states:
This places legal duties
upon suppliers, installers,
managers, coordinators
supervisors and users.
Avoiding build failure
5.1.2
BS 5975-1:2024 clause 5.1.3 provides a summary of risks requiring control relating to the
building, execution and implementation of temporary works. These can be mitigated or
controlled as follows:
Build, execution and implementation risk
1. The site team assessing execution risks
2. The project team reviewing execution risk assessment
3. The TWC determining the implementation risk classification referring to Table 1
4. Issuing permits to bring into use and take out of use
5. TWS carries out regular monitoring, maintenance and quality control
5.1.3
The following shows the relationships between the temporary works design team. This is for
illustration purposes only.
TWC
Determines implementation risk classification to
detemine who issues permits and how regularly
inspection is undertalen
Site team
Completes execution risk
assessment
Project team
TWS
Reviews execution risk
assessment
Carries out quality control
and monitors the build and
removal