5.4 Inspecting and testing temporary works
5.4.12
The following temporary works register example identifies who issues the temporary works
permit and who carries out the final inspection prior to bringing into use.
BS 5975-1:2024
clause 11.3(e)(h) identifies the temporary works supervisor (TWS) should carry out checks at
appropriate stages and the final check. However, for complex or innovative designs, BS 59751:2024 clause 13.1.8 states this could be the temporary works designer (TWD).
Shows the implementation
risk classification.
Shows the frequency of inuse inspections as per the
ITP and the implementation
risk classification.
Shows who checks during
use. For complex or
innovative designs, this
could be the TWD.