4.3 Design and build guidance
4.3.1
BS 5975-1:2024 clause 12.3.1 states that the temporary works designer must choose the
appropriate design standards and other technical guidance. In addition, BS 5975-1:2024 clause
12.7.3(b) and (c), states that the temporary works design check would require analysis of
suppliers or manufacturer’s techincal data to determine the structure’s or materials limitations
are not affected by actual site conditions. BS 5975-1:2024 clause 12.3.1 also states that any
British Standards, or other design guidance, or software used, should be summarized in the
design outputs by the TWD and issued to the TWDC.
Design and build guidance
4.3.2
The following are selected publications relating to design and build considerations for a range of
temporary works structures and equipment used in the construction industry available to
purchase from ICE Publishing.
Temporary Works principles of design and
construction provides an authoritative and
comprehensive guidance on temporary works
for practising engineers working for a
contractor or builder, or a design consultant,
or those intending to gain the technical
elements of skill needed to perform effectively
in these roles.
Temporary Works further principles of design
and construction part two includes an
additional 20 chapters with updated industry
practices and provides an authoritative and
comprehensive guidance on key areas of
temporary works for practising engineers.
British and European Standards
4.3.3
European Standards (EN) are technical standards adopted by the European community drafted
and maintained by the European Committee for Standardization (CEN). British Standards (BS)
are produced by the BSI Group, incorporated under royal charter, and are the UK Government’s
designated national standards body. Following harmonization, some British Standards have been
replaced or superseded by European Standards and commonly referred to as BS EN’s. In
addition, BSI Group develops Publicly Available Specifications (PAS) in response to urgent
industry need that are developed more quickly than BS’s.
© mytemporary.works | How to manage temporary works in construction
95