Exercise 3
The design brief
LIST the information you should provide to the temporary works
designer AND the information the temporary works designer should
provide to you plus the considerations and KEY FEATURES the proposed
designed solution should include.
Scenario 1
You are a site agent working for a civil engineering contractor and you have been tasked with
installing drainage for a new 4-storey office block.
The redundant factory has been demolished, and the ground contamination and the Japanese
knotweed have been removed. The foundation for the new 4-storey office block has been recently
completed.
Your task, using the site plan on page 39, is to complete the design brief for a trench lining
system to support the vertical sides of the excavation to enable you to install the drainage.
2
36
LIST the information the temporary works designer should provide to the
temporary works coordinator and the considerations and key features the proposed
designed solution should include.