Temporary works training course study Pack preview - Book - Page 47
Exercise 5
Table 1 and Table 2
Using BS 5975 'Table 1' and 'Table 2', IDENTIFY the design check category, the implementation
risk classification and who would be authorised to issue permits relating to structures both ABOVE
and BELOW the ground.
By completing this 1. Explain what should be addressed in the temporary works
exercise, you will be
process.
able to:
2. Record who is responsible for specific actions for the safe
execution of temporary works.
By completing this 6.6 (TWS) 6.7 (TWC) Explain the different categories of design
exercise,
you
will check and their relative implications.
have completed these
8.1 (TWS) 9.1 (TWC) Explain the importance of implementation
learning outcomes:
risk classification in relation to the execution, maintenance, and
removal of temporary works on site.
© 2B Trained Ltd | Temporary Works Training Course l Study Pack